Taltson Hydroelectricity Expansion
Overview
Expanding Taltson will deliver long-term, reliable, clean hydro power for the Northwest Territories, supporting communities, industry growth, and a lower-carbon future.
Anticipated benefits
- Supports a cleaner, more reliable northern power system by expanding hydro capacity and reducing diesel dependence.
- Strengthens long-term energy security for communities and supports future industrial development.
- Creates economic opportunities through construction, operations, and Indigenous partnership models.
- Advances reconciliation through shared planning, co-development, and potential ownership pathways.
Project at a glance
- Key Partners: Deninu Kųę́ First Nation, Fort Resolution Métis Government, Fort Smith Métis Council, Hay River Métis Government Council, Łutsel K’e Dene First Nation, Northwest Territories Métis Nation, Salt River First Nation, Yellowknives Dene First Nation, federal departments (NRCan, CIRNAC, Infrastructure Canada).
- Region: South Slave to North Slave transmission corridor
- Status: Planning, partnership development, and technical work. Pre-construction, engineering, and engagement are underway, with updated technical and financial analysis ongoing.
- Phase: Expansion of the existing Taltson hydro system and a transmission line connecting the North Slave.
- Capacity: Existing ~22 MW; proposed 60MW expansion more than doubles capacity for territorial needs.
- Funding: GNWT, with federal engagement underway; previous federal support for feasibility and engineering.
Proposed location
This image needs to be replaced with an actual map
Current activity and next steps
What’s happening now
- The GNWT is advancing Indigenous partnership discussions on governance and potential ownership models.
- Updated engineering, financial analysis, and system modelling work underway to reflect current costs and power demand.
- Federal briefings and alignment with national clean energy, security, and critical minerals priorities.
Next Steps
- Completing refreshed feasibility work and updated load/demand analysis for prospective customers.
- Advancing formal partnership structures with Indigenous governments.
- Developing updated federal funding proposal
- Preparing public information updates, technical summaries, and engagement materials.
Project timeline
Item number 1 with a status of in progress
2026
Updated engineering, planning, and partnership development
Item number 2 with a status of in progress
2026–2027
Regulatory application and federal funding submission
Item number 3
2027+
Detailed design, Environmental Assessment, financing and procurement
Item number 4
Long-term
Construction phase 4-5 years
Taltson Hydroelectricity Expansion in the news
August 22, 2026
Premier R.J. Simpson on staying united amid new U.S. tariffs and strengthening Canada’s economic resilience
Premier R.J. Simpson issued the following statement today in response to the United States imposing new tariffs on Canadian goods following recent Canada-U.S. trade negotiations: “After weeks of...
July 6, 2026
Minister Caroline Wawzonek and Minister Caitlin Cleveland mark the conclusion of the 2026 Energy and Mines Ministers’ Conference in Yellowknife
Minister Caroline Wawzonek and Minister Caitlin Cleveland issued the following statements today as the 2026 Energy and Mines Ministers’ Conference concluded in Yellowknife, marking the end of the...
June 10, 2026
Minister Wawzonek provides Taltson Update: Building on Last Week’s Steering Committee Visit
Following meetings with the Taltson Steering Committee in Yellowknife last week, there is renewed momentum behind the Taltson Hydro Expansion Project and a clearer path for the work ahead. Taltson is...